2025ArbitrationHigh CourtLatestLegalNovember 2025

Veritable Party to the Arbitration Agreement & Privity of Contract

Judgment dated 3.11.2025 of the High Court of Bombay in Arbitration Appeal Nos.47, 48 and 49 of 2013 of Rajasthan State Coop Oil Seed Growers Federation Ltd (Tilam Sangh)  Vs.   B.G. Shirke Construction Technology Pvt. Ltd and another

No Room for Re-Litigation : Bombay HC Message to Veritable Party

Sangh had engaged National Engineering Cooperative Ltd as PMC for setting up silos for storage and process of mustard seeds at three locations vide agreement dated 6.11.1987.   PMC had engaged the respondent to carry out the works vide agreement dated 28.9.1989.

Shirke completed the works on 20.1.1990, completion certificate was issued on 31.10.1993.  Shirke filed claims for payment and ultimately, filed suits.  On section 8 AA application of PMC, the disputes were referred to arbitration.  

The Arbitral Tribunal passed the award on 2.6.2003 with interest.

On 18.7.2013, the District Court, Pune, upheld the award and also ruled that the PMC merely an agent. Section 34 petition of PMC was allowed and tht of Tilam Sangh was rejected.

HELD that the agreement is  not only dependent on NHEC role as a PMC as contracted by Sangh under the PMC Contract but also akes it explicitly clear that if Sangh or Sirke have any disagreement with NHEC, the disagreement would be amenable to arbitration under clause 23.1.4 of the agreement.  Thus, the agreement expands and extrapolates the reach of arbitration jurisdiction in the agreement to Sangh too.

Veritable Party to the Arbitration Agreement & Privity of Contract

PMC Contract and the Agreement have a common subject matter.   PMC is but a consultant of Sangh which had authorized PMC to appoint Shirke.  The Agreement was authorized by Sangh.   The Agreement being on a principal-to-principal basis can only mean that Shirke is not an agent of NHEC.   PMC Contract is purely to enable NHEC to carry out the specific tasks assigned to NHEC by Sangh.   The risk and reward from the project flow to Sangh.  The only reward for NHEC is the fees and the incentive for timely completion. Therefore,

Therefore, the obligation to pay, which is a determination on merits, cannot be visited upon NHEC, which werely a PMC.

It cannot be contended that it is customary for a project management consultant to undertake the liability owed by the principal employer owed to the sub-contractors.

PMC Not Liable for Principal Employer’s Liability to Sub-contractor – Bombay HC Defines Boundaries in Arbitration

Bombay HC – A Judicial Analysis of Consultant’s Role, Liability – of Sub-Contractor, Veritable & Contractual Parties

Decoding PMC Liability to Sub-Contractor & Arbitration Scope : Bombay HC Ruling

Consultant, Principal Employer, Sub-Contractor – Accountability & Arbitration – Bombay HC Decision in B.G. Shirke case

Expanding Arbitration & Jurisdiction: Bombay HC on Privity and PMC Liability in B.G. Shirke case

Leave a Reply

Your email address will not be published. Required fields are marked *

I HAVE READ THE DISCLAIMER AND AGREE TO IT.

User Acknowledgement

By proceeding further and clicking on the "AGREE" button herein below, I acknowledge that I of my own accord wish to know more about LegalDeli for my own information and use. I further acknowledge that there has been no solicitation, invitation or inducement of any sort whatsoever from LegalDeli or any of its members to create an Attorney-Client relationship through this knowledge site. I further acknowledge having read and understood the Disclaimer below.

Disclaimer
About: This knowledge-site (www.LegalDeli.in) is owned and operated by LegalDeli (“NDA”), and is a resource for your informational and educational purposes only.

No Warranty: NDA does not warrant that any content or information contained on this knowledge-site is accurate, correct, complete or up-to-date, and hereby disclaims any and all liability to any person for any actual or threatened loss or damage caused by errors or omissions, whether such errors or omissions result from negligence, accident or otherwise. NDA assumes no liability for the interpretation and/or use of the content and/or information contained on this knowledge-site, nor does it offer any warranty of any kind, either expressed or implied in relation to such content or information.

Third-Party Links: NDA does not intend that links / URLs contained on this knowledge-site re-directing users to third party websites be considered as referrals to, endorsements of, or affiliations with any such third party website operators. NDA is not responsible for, and makes no representations or warranties, express or implied, about the content or information contained on such third party websites to which links may be provided on this knowledge-site.

No Legal Advice: By clicking ‘I agree’ and proceeding further, you acknowledge, represent and undertake that you on your own accord wish to know more about NDA, its capabilities and research content and information contained on the knowledge-site, for your own knowledge and personal use. The content and information contained on this knowledge-site should not be construed as nor relied upon as legal advice. You as a reader or recipient of content or information contained in this knowledge-site should not act, nor refrain from acting, based upon any or all of such content or information, but should always seek the advice of competent legal counsel licensed to practice the relevant law in the appropriate jurisdiction.

No Attorney-Client Relationship: This knowledge-site is not intended to be and you should not consider the content or information contained therein to be an advertisement, solicitation, inducement or invitation for an Attorney-Client relationship. Transmission, receipt or use of this knowledge-site, including content and information contained therein, does not constitute nor create an Attorney-Client relationship between NDA and you.