Mass Transfers of BOSH Employees Is Not Substitute For Retrenchment
Judgment dated 19.11.2026 of the High Court of Bombay in Writ Petition No.13945 of 2026 of Bosh Ltd and others Vs. NETW Kam Sangathana and another
The Petition is filed by the employer-Bosch Ltd. challenging the judgment and order dated 29 September 2026 passed by the Industrial Court, Nashik allowing Complaint (ULP) No.46 of 2024 and setting aside transfer orders dated 7 September 2024, by which the members of Respondent Union were transferred at various places throughout the country claiming non-availability of work at Nashik Plant.
the Petitioner-employer transferred 521 workmen. The transfers are admittedly not issued in usual administrative exigencies. On the other hand, it is Petitioners’ own case that the transfers were aimed at providing meaningful work to the NETWs for whom there is no work at Nashik plant. In this pleaded case of the Petitioners, there lies an implied admission that the transfers are effected essentially to ensure that the NETWs need not be paid any wages at Nashik plant. Non-availability of work at Nashik plant is thus the only reason for transferring the workers en masse.
Though payment of lumpsum compensation may put some financial strain on Petitioner No.1, it would get relieved of the obligations to pay backwages since 7 September 2024 and of employing the workmen at Nashik plant towards implementation of the Industrial Court’s order. On the other hand, NETWs are out of service for substantial time. The Red-Light Activation has begun from the year 2021 and for the past five years they are not in continuous service with Petitioner No.1. In such circumstances, payment of lumpsum compensation would provide them some solace from the employer, which does not have sufficient work for their continuous employment. Considering the peculiar facts and circumstances of the present case, in my view, it would be appropriate to put an end to the entire dispute by directing payment of lumpsum compensation of Rs.25,00,000/- to each NETW involved in the Petition (Complaint (ULP) No.46 of 2024).