Bombay HC – No Claim Certificate Bars Subsequent Arbitral Claim for Damages
Judgment dated 20.11.2026 of the High Court of Bombay in Commercial Arbitration Petition No.146 of 2021 with Interim Application No.2785 of 2024 of Vishal Associates Vs. Hindustan Construction Company Limited
No Claim Certificate signed and given voluntarily by the contractor bars subsequent arbitral claims for damages – Arbitral Award dismissing the claim of the contractor was upheld in Section 34 petition.
the Petitioner had also voluntarily issued a “Work Completion and No-Claim Certificate” dated 25th July 2011, confirming that it was not in a position to undertake or execute any further work due to its internal difficulties. xix. Sometime in December 2011, in view of the No-Claim Certificate and the final bill, the Respondent paid the outstanding amount of Rs. 34,00,000/- to the Petitioner in full and final settlement and the Petitioner had admitted the receipt of the aforesaid amount. xx. Thereafter on 7th May 2012, after a lapse of more than ten months from the date of the No-Claim Certificate and after having received full and final statement for the work executed by it in December 2011, the Petitioner issued a demand notice to the Respondent alleging that it was entitled to damages and compensation on account of the alleged delay in payment of amounts under the Work Order. The Petitioner thereafter invoked the dispute resolution mechanism stipulated under the Work Order. xxi. Mane Uploaded on – 20/11/2026 On 12th June 2012, the Respondent replied to the aforesaid demand notice, Page 6 of 40 Downloaded on – 22/11/2026 00:50:36 07-CARBP-146-21 WITH IAL (FINAL).DOCX denying the claims raised by the Petitioner and the Respondent pointed out that all claims of the Petitioner had already been fully and finally settled and satisfied. In particular, the Respondent relied upon the No-Claim Certificate dated 25th July 2011, pursuant to which the Petitioner had expressly confirmed that no further claims remained outstanding against the Respondent. The Respondent further contended that the claims raised in the Petitioner’s demand notice were an afterthought, raised with mala fide intention of extracting further monies from the Respondent. xxii. On 23rd August 2012, the Petitioner sent a letter of even date to the Respondent for appointment of learned Sole Arbitrator. On 24th September 2012, the Respondent by intimation letter of even date informed the Petitioner of the appointment of learned Sole Arbitrator.
By way of the impugned arbitral award the learned Sole Arbitrator dismissed the claim of the Petitioner and imposed a cost of Rs. 1,00,000/-. The learned Sole Arbitrator on the basis thereof did not allow the claim as made by the Petitioner in the statement of claim preferred before the learned Sole Arbitrator.