Legal

Arbitral Award – Liquidated Damages

GRE was awarded contract of Rs.116 crores to construct twelve mounded bullets for LPG storage at HPCL refiner.  The project was to be completed by 5.12.2007 but it was completed on 2.2.2010.

GRE requested for extension on four times with a request to waive liquidated damages.  However, the extensions were granted extension with four change orders without prejudice to the liquidated damages clauses 5.6 and 10 of GCC.  GRE did not raise any protest.

Disputes arose out of computation of liquidated damages and also withholding various other amounts leading to arbitration proceedings.

By the Arbitral Award dated 2.5.2018, the Arbitral Tribunal held in favour of  GRE that HPCL ought not to have withheld the amounts of Civil Works, Under Insurance, Customs Duty variation, Service Tax, Dished Ends and liquidated damages.

HELD that Clause 8.6 provides that the project was subject to inspection by various agencies of the Government of India and to make recovery if recommended from the running bills.  Admittedly, no external agency was at all involved in HPCL’s decision to withhold the amount.  Central Vigilance Commission is an internal department of HPCL and is not an inspection agency of the Government of India to withhold amounts as per clause 8.b of the contract.

HELD that the impugned Arbitral Award on liquidated damages is perverse and manifestly arbitrary for want of reasoning, and also being contrary to the fundamental policy of the law of India in relation to liquidated damages.

The Arbitral Tribunal was expected to deal with the question whether it is difficult or impossible to prove the loss in the instant case.   One would have expected the Tribunal to then deal with whether the amount of 0.5% per week of delay which is capped at 5% of the contract value, is reasonable, if it is difficult to prove the loss.

There was no consideration whatsoever on the causation of delay and which party was responsible for the delay.

Judgment dated 18.6.2025 of the High Court of Bombay in Commercial Arbitration Petition No.984 of 2018 of HPCL   Vs.  G.R.Engineering Private Limited

Leave a Reply

Your email address will not be published. Required fields are marked *

I HAVE READ THE DISCLAIMER AND AGREE TO IT.

User Acknowledgement

By proceeding further and clicking on the "AGREE" button herein below, I acknowledge that I of my own accord wish to know more about LegalDeli for my own information and use. I further acknowledge that there has been no solicitation, invitation or inducement of any sort whatsoever from LegalDeli or any of its members to create an Attorney-Client relationship through this knowledge site. I further acknowledge having read and understood the Disclaimer below.

Disclaimer
About: This knowledge-site (www.LegalDeli.in) is owned and operated by LegalDeli (“NDA”), and is a resource for your informational and educational purposes only.

No Warranty: NDA does not warrant that any content or information contained on this knowledge-site is accurate, correct, complete or up-to-date, and hereby disclaims any and all liability to any person for any actual or threatened loss or damage caused by errors or omissions, whether such errors or omissions result from negligence, accident or otherwise. NDA assumes no liability for the interpretation and/or use of the content and/or information contained on this knowledge-site, nor does it offer any warranty of any kind, either expressed or implied in relation to such content or information.

Third-Party Links: NDA does not intend that links / URLs contained on this knowledge-site re-directing users to third party websites be considered as referrals to, endorsements of, or affiliations with any such third party website operators. NDA is not responsible for, and makes no representations or warranties, express or implied, about the content or information contained on such third party websites to which links may be provided on this knowledge-site.

No Legal Advice: By clicking ‘I agree’ and proceeding further, you acknowledge, represent and undertake that you on your own accord wish to know more about NDA, its capabilities and research content and information contained on the knowledge-site, for your own knowledge and personal use. The content and information contained on this knowledge-site should not be construed as nor relied upon as legal advice. You as a reader or recipient of content or information contained in this knowledge-site should not act, nor refrain from acting, based upon any or all of such content or information, but should always seek the advice of competent legal counsel licensed to practice the relevant law in the appropriate jurisdiction.

No Attorney-Client Relationship: This knowledge-site is not intended to be and you should not consider the content or information contained therein to be an advertisement, solicitation, inducement or invitation for an Attorney-Client relationship. Transmission, receipt or use of this knowledge-site, including content and information contained therein, does not constitute nor create an Attorney-Client relationship between NDA and you.