2025April 2025High CourtLatestLegalReal Estate

Section 36(1)(a) of the Maharashtra Public Trusts Act, 1950 – Extension of time for sale deed

By the order dated 6.2.2001, permission to sell its land at Nagala Park, Kolhapur, in favour of respondent no.5 was granted to the petitioner Trust.

However, the sale-deed could not be executed within the stipulated period of one year due to procedural and legal impediments.

In 2019, the petitioner applied to the Joint Charity Commissioner for extension of time to execute the sale-deed.   However, this was rejected on 2.1.2025 finally after two rounds of litigation.  It was held that permitting the sale at the old rate, without re-evaluation or inviting fresh bids, would be detrimental to the interest of the Trust.

HELD that the alienation of the Trust property is in the “interest, benefit or protection” of the Trust.  The authority is under a statutory duty to protect the Trust’s interest and ensure that any alienation of trust property is undertaken in a manner that secures maximum value and benefit to the beneficiaries.

The stipulation of execution of sale deed in one year i.e. 6.2.2022 was an integral part of the statutory permission and cannot be treated as a mere formality or directory in nature.   The imposition of such a timeline is not without purpose, rather, it serves a vital function of protecting the interest of the Trust by ensuring that the transaction is completed promptly and without any delay, thereby safeguarding the Trust from potential undervaluation of its assets in a fluctuating real estate market.

In this case, the petitioner seeks to revive transaction almost 25 years after initial permission was granted.   To permit completion of the sale at the price of 2001, without any re-evaluation or fresh offers, would be manifestly detrimental to the interest of the Trust and would amount to defeating the very object and spirit of Section 36 of the Trust Act.

It is well settled that even upon remand, the Charity Commissioner retains the discretion to accept or reject the proposed transaction, provided the decision is founded upon sound reasoning and is in consonance with the object and mandate of Section 36 of the Act.

Judgment dated 7.4.2025 of the High Court of Bombay in Writ Petition No.4373 of 2025 of Commission on Ecumenical Mission and relations of the Presbyterian Church (USA)   Vs.  The state of Maharashtra and others

 

 

Leave a Reply

Your email address will not be published. Required fields are marked *

I HAVE READ THE DISCLAIMER AND AGREE TO IT.

User Acknowledgement

By proceeding further and clicking on the "AGREE" button herein below, I acknowledge that I of my own accord wish to know more about LegalDeli for my own information and use. I further acknowledge that there has been no solicitation, invitation or inducement of any sort whatsoever from LegalDeli or any of its members to create an Attorney-Client relationship through this knowledge site. I further acknowledge having read and understood the Disclaimer below.

Disclaimer
About: This knowledge-site (www.LegalDeli.in) is owned and operated by LegalDeli (“LD”), and is a resource for your informational and educational purposes only.

No Warranty: LD does not warrant that any content or information contained on this knowledge-site is accurate, correct, complete or up-to-date, and hereby disclaims any and all liability to any person for any actual or threatened loss or damage caused by errors or omissions, whether such errors or omissions result from negligence, accident or otherwise. LD assumes no liability for the interpretation and/or use of the content and/or information contained on this knowledge-site, nor does it offer any warranty of any kind, either expressed or implied in relation to such content or information.

Third-Party Links: LD does not intend that links / URLs contained on this knowledge-site re-directing users to third party websites be considered as referrals to, endorsements of, or affiliations with any such third party website operators. LD is not responsible for, and makes no representations or warranties, express or implied, about the content or information contained on such third party websites to which links may be provided on this knowledge-site.

No Legal Advice: By clicking ‘I agree’ and proceeding further, you acknowledge, represent and undertake that you on your own accord wish to know more about LD, its capabilities and research content and information contained on the knowledge-site, for your own knowledge and personal use. The content and information contained on this knowledge-site should not be construed as nor relied upon as legal advice. You as a reader or recipient of content or information contained in this knowledge-site should not act, nor refrain from acting, based upon any or all of such content or information, but should always seek the advice of competent legal counsel licensed to practice the relevant law in the appropriate jurisdiction.

No Attorney-Client Relationship: This knowledge-site is not intended to be and you should not consider the content or information contained therein to be an advertisement, solicitation, inducement or invitation for an Attorney-Client relationship. Transmission, receipt or use of this knowledge-site, including content and information contained therein, does not constitute nor create an Attorney-Client relationship between LD and you.